Address:
7540 Confederate Park Rd.
Fort Worth, TX
76108

Email Us

Phone: 817.237.9050
Texas: 800.745.PUMP
Fax: 817.237.6573

 

 

 

 
 
   
 
Picture of Silo Build
 

Pumps and Slipform System Prove a Formidable Duo in Texas Silo Build

The one-two punch of a well-designed slipform system and solid concrete pump performance has helped a quartet of cement storage silos rise at an impressive clip. One of the final phases in cement producer Holnam, Inc.'s massive Midlothian, TX plant expansion, each silo measures 60 feet in diameter by 216 feet high, and will eventually be used to store 14,500 metric tons of cement.

Sixteen Silos, No Waiting
Expansion of Holnam's Midlothian site actually began nearly three years ago with construction that essentially doubled the processing capabilities of the plant to one million metric tons per year, according to Glen Stewart, superintendent for Borton, L.C., general contractor for the project.

"This phase is to create storage capacities more in line with what the plant is able to produce now. At the start of construction back in 1998, Holnam had nine silos onsite; we added three a while back and these four will bring their total to sixteen silos. The four new silos alone will afford the company an additional 58,272 metric tons of storage.

Going Deep
The massive weight of each silo when full, dictated a heartier-than-normal slab construction. In this case, the slab is actually four circular mats, each measuring roughly 15 feet wide (60-feet to silo center) and 6 1/2-foot thick. That, however, is only the tip of this proverbial iceberg.

"The circular slabs sit on 100 pilings each measuring four feet in diameter and reaching down to a depth of 35 feet," says Stewart. "The mats alone took about 2,700 yards of concrete. Because it is difficult to get such huge volumes out to this location at one time, Central Concrete Pumping (Ft. Worth, TX), using 47-meter and 36-meter pumps, did that in two pours which were completed in 12 hours. From there we started the vertical rise of the silos which, by project's end, will have taken an additional 14,000 yards."

Giving Them the Slip
As is the case with virtually all silo projects, steady upward progress is ensured by use of a slipform system. The system in use at the Midlothian expansion, designed and built by Bow, NH-based Scanada International, Inc., features a series of 104 hydraulic jacks, 16 of which were rated for three tons, 84 of which had six-ton capacities; and 4 jacks with 22-ton capacities.

"The full lifting capacity of the system in place at Midlothian is 640 tons," says Klaus Hieronymus, Scanada's general manager. "To some that might seem exceptionally high. However, when you consider that, as it rises, the slipform system will be carrying a work crew - in this case about 120 workers, equipment, walkways, tons of rebar and the weight of the forming system itself, suddenly 640 tons doesn't seem excessive at all."

Using a Schwing BPL 4000 line pump, concrete was pumped in 8-inch increments, with the slipform system set to raise the form at seven minute per inch moves. That rate, however, was adjustable, says Stewart.

"The forms themselves are four feet tall and we like to keep our concrete wet down to about 32 inches. So if the mix stars setting faster than we like, we can adjust the system timer to rise slightly faster. Conversely, if concrete isn't setting up sufficiently, we can slow the rate down. The slipform system performed just as we had anticipated allowing us to maintain a steady rate of 10 inches of rise per hour. With a round-the clock operation we were doing 20 feet of silo each day and had the silos poured in 14 days."

Hot on the Bottom
To accommodate both the downward weight loads and a metal loadout hopper, wall thicknesses from the base of each silo up to 87 feet were a robust 36-inches. At that 87-foot point, the walls tapered to a thickness of 14-inches and maintained that thickness to the top of the silo. The difference in wall thicknesses made some modification to the standard 4000 psi mix necessary as well.

"The thick walls at the base of each silo had a tendency to generate a good deal of heat," says Stewart. "The temperatures coming off that mix - even with a cool 40°F air temp - were about 95°F. To offset those high temps we used a Master Builder Pozzolith 300R set retarder. Obviously, as we got to the higher parts of the walls, where the thicknesses come down to 14 inches, the heat was no longer present so we had to move to an accelerator, in this case, an Pozzolith NC 534 accelerator, again from Master Builder."

All concrete was supplied by Cleburne, TX-based Transit Mix, Inc. which, according to Central CP's Carl Walker, really rose to the occasion for this project.

"We just can't say enough about what Transit Mix did, both in terms of logistics and quality of service. On the slab pour, they had 18 trucks running between the site and Transit Mix's plant in Cleburne about 20 miles away and never missed a beat. For the slipform portion of the job, they set up a two batch plants onsite - one as a backup - and again, the marathon pour went off without any major problems at all."

Friction in the Line
In addition to the temperatures generated by lower wall densities, Borton had to also deal with loss of moisture in the mix from other causes.

"We used a fairly sizeable amount of 5 1/2-inch pipe on this project," says Stewart. "Taking into consideration the pipe that runs from the line pump to the base of the silos, then up the total height of the silo, then to the various reaches atop each silo, you are looking at as much as 230 feet of vertical pipe and another 250 feet of horizontal pipe. And anytime you pump concrete through that amount of pipe, friction is going to take its toll. For that reason, we opted to keep the mix a bit on the wetter side - with a slump of 5 to 5 1/2 inches. That wetter mix also seemed to be better at getting through the rebar and into the forms."

 
 
   
 
Picture of Silo Build
 

Rebar was definitely in ample supply in all facets of the project. Stewart estimates that the mat alone contains about 300 tons of # 11 bar and the silos have another two million lbs. of steel running through them.

Placement atop each of the four silos was made possible through use of a "swing-boom" system in which concrete is pumped into four swiveling delivery towers. Using gates, hoses to three of the towers are kept closed while the fourth accepts concrete. The process is repeated until all areas of all four silos have been poured.

Making it Happen
Despite the abundance of rebar, a number of varied mix designs and a fairly decent height to which to pump, Stewart says Central Concrete Pumping and its Schwing pumps ensured that getting concrete down was never a problem.

"There were areas in which the mats overlap each other and the bar got very dense, but the combination of a good mix and solid pump performance allowed us to pour those areas - and others - without a hitch. I was really pleased with the level of service we got from Central Concrete Pumping. They went the extra mile to make certain all possibilities were covered, going so far as to keeping a spare pump on hand in the event one of theirs failed. A failure never did occur, but its nice to have that peace of mind in knowing a breakdown won't spell disaster. On a project such as this, continuous delivery is the real key to success and we definitely got that."

The Holnam Midlothian expansion is slated for total completion by June 1st of this year.

# # #

General Contractor: Borton L.C., Hutchinson, KS
Pumping Contractor: Central Concrete Pumping, Ft. Worth, TX
Ready Mix Supplier: Transit Mix, Cleburne, TX
Pumps: Schwing 47-meter and 62-meter boom pumps, Schwing BPL 4000 line pump.